City of Fond du Lac – Weekly Construction Update

The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.

All anticipated construction activities are weather dependent. 

Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
September 28 to October 2: The grading contractor will begin cutting road to subgrade and placing base aggregate.
Traffic Impacts: Western Avenue is closed to traffic between the Macy St & Oak St. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Elm Street – South Street to Western Avenue
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
September 28 to October 2: The sewer contractor will finish storm sewer main and lateral installation.
Traffic Impacts: Elm Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Morris Street – W. 9th Street to W. 12th Street
Schedule: May through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
September 28 to October 2: The restoration contractor will continue placing topsoil and seeding terraces and restoration areas behind walk.
Traffic Impacts: Morris Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Griffith Street – Morris Street to east dead end
Schedule: August through September
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
September 28 to October 2: The restoration contractor will place topsoil and seed terraces
Traffic Impacts: Griffith Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Emma Street – S. Seymour Street to east dead end
Schedule: August through September
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
September 28 to October 2: The concrete contractor will prep and pour north side pavement and curb and gutter towards the end of the week.
Traffic Impacts: Emma Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Drury Place – Hillcrest Lane to Seymour Street
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
September 28 to October 2: The sewer contractor will continue installing water and sanitary laterals.
Traffic Impacts: Drury Place is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
September 28 to October 2: The concrete contractor will begin curb and gutter installation.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.