The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.
All anticipated construction activities are weather dependent.
Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
June 15 to June 19: Communication utilities will continue their relocation work.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
CTH K – STH 23 to USH 151
Schedule: May through August
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of CTH K. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete curb & gutter, asphalt roadway, permanent signing, and other incidentals.
June 15 to June 19: The County will continue constructing the storm sewer between Hunter Ave and the Agnesian Hospice Home.
Traffic Impacts: CTH K between STH 23 and USH 151 is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
June 15 to June 19: The grading contractor will continue cutting road and placing aggregate. The Concrete contractor will begin fine grading ahead of paving operation. Weather pending, there is a chance they may begin paving at the end of the week. The electrical contractor will begin installing conduit for lighting on the west side of the bridge at the end of the week.
Traffic Impacts: Western Avenue is closed to traffic. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Traffic Impacts Macy Street is closed to traffic at Court Street. Macy Street will be two-way traffic from Second Street to Court Street.
Ruggles Street – S. Hickory Street to Mary’s Avenue
Schedule: May through July
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
June 15 to June 19: No work anticipated.
Traffic Impacts: Ruggles Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Morris Street – W. 9th Street to W. 12th Street
Schedule: May through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
June 15 to June 19: Utility contractor will continue with water and sanitary lateral installation.
Traffic Impacts: Morris Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Lincoln Avenue Storm Sewer – Portage Street to 200 FT south
Thomas Street – Lincoln Avenue to Fond du Lac River
Schedule: April through May
Description: The project includes storm sewer and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
June 15 to June 19: Restoration contractor will begin placing topsoil, seed, and hydro mulch terraces.
Traffic Impacts: Thomas Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. Temporary No Parking on South Side of Thomas Street until work is completed.
Montana Street – Lake Street to N. Hickory Street
Schedule: May through June
Description: The project includes gas main and service relocations, reconstruction of storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, and restoration/landscaping.
June 15 to June 19: Restoration contractor will begin placing topsoil and seeding and hydromulching terraces.
Traffic Impacts: Montana Street is closed to traffic from Lake Street to N. Hickory Street.
Date posted: June 15, 2026