Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
October 26 to October 30: The concrete contractor continues placement and later in week the electrical contractor will be working on light pole bases for the new traffic signals.
Traffic Impacts: Western Avenue is closed to traffic between the Macy St & Oak St. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.

Elm Street – South Street to Western Avenue
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 26 to October 30: The concrete contractor will place curb and gutter, sidewalks and driveways.
Traffic Impacts: Elm Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.

Drury Place – Hillcrest Lane to Seymour Street
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 26 to October 30: The electrical contractor will install conduit and mid-week concrete contractor will start.
Traffic Impacts: Drury Place is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs.

Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
October 26 to October 30: The county will continue constructing sidewalks and driveway approaches.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.