City of Fond du Lac – Weekly Construction Update

City of Fond du Lac – Weekly Construction Update

The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.

All anticipated construction activities are weather dependent. 

Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
October 5 to October 9: The grading contractor will continue cutting road to subgrade and placing base aggregate. The concrete contractor will begin work on the approach slab on the east side of the bridge.
Traffic Impacts: Western Avenue is closed to traffic between the Macy St & Oak St. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Elm Street – South Street to Western Avenue
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 5 to October 9: The grading contractor will begin cutting road to subgrade and placing base aggregate.
Traffic Impacts: Elm Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Morris Street – W. 9th Street to W. 12th Street
Schedule: May through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
October 5 to October 9: The restoration contractor will finish placing topsoil and seeding terraces and restoration areas behind walk. There is a chance the asphalt contractor will begin fine grading roadway ahead of asphalt operation later in the week.
Traffic Impacts: Morris Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Griffith Street – Morris Street to east dead end
Schedule: August through September
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 5 to October 9: The restoration contractor will finish placing topsoil and seed terraces. There is a chance the asphalt contractor will begin fine grading roadway ahead of asphalt operation later in the week.
Traffic Impacts: Griffith Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Emma Street – S. Seymour Street to east dead end
Schedule: August through September
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 5 to October 9: The concrete contractor will pour north side pavement and curb and gutter.
Traffic Impacts: Emma Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Drury Place – Hillcrest Lane to Seymour Street
Schedule: August through October
Description: The project includes gas main and service relocations, reconstruction of water main and laterals, partial roadway, and restoration/landscaping.
October 5 to October 9: The sewer contractor will continue installing storm laterals.
Traffic Impacts: Drury Place is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.

Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
October 5 to October 9: The contractor will complete the concrete curb and gutter installation.  The county will construct driveway aprons.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours. 

Date posted: October 4, 2026