The City of Fond du Lac is providing a weekly update on construction projects located within the corporate boundary. The Weekly Construction Updates and Construction Map are posted on the City’s Website at www.fdl.wi.gov.
All anticipated construction activities are weather dependent.
Stow Street Bridge
Schedule: June 17 through September 15
Description: 0.034-mile project involving removals, grading, aggregate, asphalt pavement, structure replacement, curb and gutter, concrete sidewalk, storm sewer, erosion control, traffic control, and restoration.
July 6 to July 10: The contractor will form, tie steel, and pour west abutment.
Traffic Impacts: Stow Street is CLOSED to pedestrian and vehicle traffic through the duration of the project.
Pioneer Road – CTH V to Fond du Lac Avenue
Schedule: April through October
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of Pioneer Road. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete sidewalk and curb & gutter, asphalt roadway, roadway lighting, permanent signing, and other incidentals.
July 6 to July 10: Communication utilities will continue their relocation work. The City will remove the old hydrants.
Traffic Impacts: Pioneer Road between CTH V and Fond du Lac Avenue is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
CTH K – STH 23 to USH 151
Schedule: May through August
Description: Fond du Lac County Highway Dept in partnership with the City of Fond du Lac are reconstructing this segment of CTH K. The construction includes common excavation, sanitary sewer, watermain, storm sewer, concrete curb & gutter, asphalt roadway, permanent signing, and other incidentals.
July 6 to July 10: The City will be adjusting water valves. The county will complete the preparation for the curb and gutter installation. Traffic to Agnesian Hospice Home of Hope should access the facility from the south via STH 23.
Traffic Impacts: CTH K between STH 23 and USH 151 is closed to traffic. Residents may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Western Avenue – Military Road to Main Street
Macy Street – Court Street to Western Avenue
Schedule: April 27 through October
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, traffic signals and restoration/landscaping.
July 6 to July 10: The concrete contractor will fine grade concrete pavement on Western Ave and Macy Street. The electrical contractor will begin installing light pole bases and pull boxes.
Traffic Impacts: Western Avenue is closed to traffic. Residents, business owners, jurors and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Traffic Impacts Macy Street is closed to traffic at Court Street. Macy Street will be two-way traffic from Second Street to Court Street.
Ruggles Street – S. Hickory Street to Mary’s Avenue
Schedule: May through July
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
July 6 to July 10: No work anticipated.
Traffic Impacts: Ruggles Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Morris Street – W. 9th Street to W. 12th Street
Schedule: May through September
Description: The project includes gas main and service relocations, reconstruction of sanitary sewer and laterals, storm sewer and laterals, water main and laterals, roadway, sidewalk and approaches, street lighting, and restoration/landscaping.
July 6 to July 10: The utility contractor continues with water and sanitary lateral installations.
Traffic Impacts: Morris Street is closed to traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED TO THRU TRAFFIC” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Date posted: July 6, 2026